Construction Submittals in Wyoming: A Contractor's Practical Guide

Writer: Crystal Peña
Crystal Peña
Nov 12
8 min read

If you've ever had a crew standing around on a commercial job because the light fixtures weren't approved yet, you already know why construction submittals in Wyoming matter. Submittals are the paperwork nobody brags about. They're also one of the quietest ways a good contractor loses money, time and the trust of a general contractor or owner.

I see it all the time when contractors make the jump from residential work to commercial, school, town or county projects. The field work is solid. The paperwork is where things slip. A missed submittal can push back an order, and in a place like Pinedale or Rock Springs, a delayed order isn't a two-day problem. It can be a two-week problem once freight and the next delivery truck come into it.

This guide walks you through what submittals are, how the review process usually works, how to build a simple submittal log, and the mistakes I'd fix first. No jargon, just what works.

What construction submittals are (and why they exist)

A submittal is anything you send to the design team or owner to show exactly what you plan to install before you install it. The specs say "a commercial-grade door closer." Your submittal says "this one, this model, this finish, here's the data sheet."

The most common types:

  • Product data: manufacturer cut sheets showing the model, size, finish and performance.

  • Shop drawings: drawings made by you, your supplier or your fabricator showing how something will actually be built or installed. Think steel, casework, trusses or ductwork.

  • Samples: physical pieces like flooring, paint colors, brick or countertop material.

  • Mock-ups: a built section on site so the architect can see the real thing.

  • Closeout items: warranties, operation and maintenance manuals, and as-built information, often due at the end of the job.

Why does anyone care? Because the architect or engineer is responsible for making sure the building matches the design. The owner wants what they paid for. And you want a written approval before you buy and install something, so you're not the one paying to rip it out later.

An approved submittal is protection. An unapproved one is a gamble.

Where submittal requirements live in your contract documents

Before you send a single cut sheet, find out what the job actually asks for. On most commercial and public projects in Wyoming, the requirements are spread across a few places:

  1. The general conditions and the submittal procedures section of the specs. This tells you the format, how many copies, whether it's paper or electronic, who it goes to and how long the review takes.

  2. Each technical specification section. Every section (concrete, doors, roofing, electrical) usually lists its own "submittals" paragraph with exactly what's required for that work.

  3. The drawings and any addenda. Sometimes an addendum changes a product, which changes what you need to submit.

  4. The project's software or portal. Larger GCs may use a project management platform. Smaller towns or special districts may still use email and PDFs.

The day you're awarded the job, pull every submittal requirement in your scope into one list. It's tedious, and it's the best hour you'll spend on the project.

How the submittal review process usually works

Every job is a little different, so always follow your contract. But the flow usually looks like this:

  1. You prepare the submittal. Gather the data sheets, drawings or samples. Mark which model, size and options apply, because a cut sheet with ten models on it and no markings will come back.

  2. You review it yourself first. Check it against the specs. Does it meet the requirements? If it doesn't, say so plainly and request a substitution the right way.

  3. You send it to the general contractor (if you're a sub). The GC reviews it, stamps it and forwards it to the architect or engineer.

  4. The design team reviews it. They return it with a status. Common ones are "approved," "approved as noted," "revise and resubmit," or "rejected." The exact wording varies by firm.

  5. You act on the response. "Approved as noted" means you can move forward, but read the notes. "Revise and resubmit" means you don't order yet.

  6. You order and install what was approved. Not something "just as good" you found later.

The part people underestimate is time. Between the GC and the architect's review windows, one round trip can eat several weeks. A "revise and resubmit" starts the clock over.

So work backward. If the steel needs approved shop drawings, plus fabrication time, plus freight into Sublette County, the submittal needs to go out a lot earlier than most people think.

Build a simple submittal log that actually gets used

You don't need fancy software to run submittals well. You need one list that someone owns and updates every week. A spreadsheet works fine for most small and mid-size contractors.

Your submittal log should include:

  • Submittal number (often tied to the spec section, like 08 71 00-01)

  • Spec section and description (for example, "Door hardware, product data")

  • Type (product data, shop drawing, sample, closeout)

  • Responsible person (you, your supplier, your fabricator)

  • Date due (based on the schedule, not on when you get around to it)

  • Date sent

  • Date returned

  • Status (approved, approved as noted, revise and resubmit, rejected)

  • Lead time for the material after approval

  • Need-on-site date

  • Notes (what the reviewer asked for)

Then sort by the need-on-site date minus lead time. Anything that's close should be at the top of your Monday meeting.

The goal is simple: nobody on your team should have to dig through email to know where a submittal stands.

The most common submittal mistakes (and how to avoid them)

These are the ones I'd fix first. None are complicated; they just take a habit.

Sending submittals late

This is the big one. Contractors treat submittals as something to deal with "when we get closer." By then, review time plus lead time has already blown the schedule. Start on day one.

Sending incomplete packages

A package missing the finish selection, the color, the sizing or the installation details gets kicked back. Every kickback costs you a full review cycle. Check the spec section's list before you send.

Not marking up cut sheets

If a data sheet shows six options, circle or highlight the one you're providing and cross out the rest. Reviewers aren't going to guess, and they shouldn't have to.

Ignoring "approved as noted" comments

The notes are part of the approval. If the architect writes "provide the stainless finish," and you install the bronze, that's on you.

Slipping in substitutions

If you want to use a different product than what's specified, follow the substitution process in the specs. A substitution hidden in a regular submittal can come back to bite you, even if it gets stamped.

No one owns the log

When "everybody" is in charge of submittals, nobody is. Assign one person. In a small company, that might be the owner's spouse, the office manager or a part-time project coordinator.

Submittals on Wyoming public and rural projects

If you're working for a town, county, school district or special district, a few things are worth knowing.

Distance changes everything. Lead times quoted to Denver or Salt Lake City aren't the same lead times to Pinedale, Jackson or a site up a gravel road. Ask suppliers for a delivered date, not a ship date.

Seasons matter. Our building window is short. If submittals drag into fall, you may be pouring concrete or setting roofing in conditions you don't want. Getting approvals early protects your summer.

Small owners may be less formal. Some small towns and districts run lean, with a part-time administrator and an outside engineer. That can mean slower turnaround. Ask early who reviews submittals and how long they usually take, then plan for it.

Documentation protects you later. Public projects often come with more paperwork at closeout and more scrutiny if something goes wrong. A clean submittal log, with dates, is your record of what was approved and when.

If you're bidding public work, it's worth reading our pre-bid meeting checklist for Wyoming contractors, too. Asking about submittal procedures at the pre-bid meeting is one of the easiest ways to avoid surprises.

A simple weekly submittal routine

If you only take one thing from this post, take this. Thirty minutes a week, same day, same time:

  1. Open the submittal log.

  2. Look at anything due in the next three weeks. Is it in progress? Who has it?

  3. Look at anything sent but not returned. Follow up with the GC or architect if it's past the review window.

  4. Look at anything returned "revise and resubmit." What's the fix, and when will it go back out?

  5. Look at anything approved. Has it been ordered? What's the delivery date?

  6. Update the schedule if anything slipped, and tell the people who need to know.

The contractors who do this well aren't smarter than anyone else. They're consistent.

How ApreGrow helps contractors with submittals and back-office systems

I've spent years on the operations side of building businesses, including a multi-state telehealth practice and a medical billing company, and I know how much money gets lost in the gaps between the field and the office. Submittals are one of those gaps.

For contractors in Wyoming, Idaho and Utah, we help build the systems that keep jobs profitable: estimating, bidding, project management and the back office. On the submittal side, that can mean:

  • Setting up a submittal log template that fits how your company works

  • Pulling submittal requirements out of the specs at the start of a job

  • Building a weekly review routine for you or your office staff

  • Coordinating with GCs, architects and suppliers so your crew isn't waiting on paperwork

  • Tying submittals into your schedule, change orders, pay apps and closeout

You can see more about our construction management support for contractors. We work in English and Spanish.

And honestly, if you're only doing one or two small commercial jobs a year, you may not need to hire anyone. A simple spreadsheet and the weekly routine above might be all it takes. When you're running several jobs at once and things are starting to slip, that's when outside help usually pays for itself.

For reference, our hourly rate is $250 billed in half-hour increments, and project-based work starts at $2,000.

FAQ: construction submittals in Wyoming

How early should I send submittals?

As early as the contract allows. Work backward from the date the material needs to be on site: subtract shipping, fabrication or manufacturing lead time, then subtract the full review time listed in the specs, then add a buffer for one resubmittal. For long-lead items, that often means the first weeks of the project.

What's the difference between "approved" and "approved as noted"?

"Approved" means you can proceed as submitted. "Approved as noted" means you can proceed, but you must follow the reviewer's comments. Always read the notes before ordering. Exact terms vary by design firm, so check the stamp.

Can I order materials before the submittal is approved?

You can, but it's at your own risk. If the submittal comes back rejected or with changes, you may be stuck with material you can't use. For anything expensive or custom, wait for the approval in writing.

Does a small subcontractor really need a submittal log?

Yes, even if it's a single page. If you're on one job with five submittals, it takes ten minutes to set up. It keeps you from forgetting anything, and it gives you a record if there's ever a dispute about what was approved.

Let's get your paperwork working for you

Submittals aren't exciting. But when they're handled well, your crews keep moving, your GCs trust you and your jobs stay profitable. If you'd like a second set of eyes on how your company handles submittals, scheduling or back-office systems, book a free 30-minute strategy call or call me at (307) 200-5167. We'll talk through what's working, what isn't, and whether you even need outside help right now.

 
 
 